Retain the façade. Transform how the building looks, feels and performs.
Dortech Architectural Systems is delivering a specialist glazing upgrade for Munroe K at the ABC Building, White Rose Park—retaining the original MAG Presslock curtain wall while replacing ageing glass with a modern solar-control specification.
Approximately 748m² of glazing has been replaced to date, supported by system-specific detailing and specially extruded replacement retaining facecaps.

Asset-focused investment in the performance and presentation of the ABC Building.
A collaborative response to an existing façade with unusual technical constraints.
A large-scale phased replacement programme delivered within retained curtain walling.
Original curtain-wall framing and a restricted 12mm glazing cavity.
A 1983 façade with ageing units, inconsistent finishes and comfort problems.
Many of the insulated glass units dated from the building’s original construction. During warmer periods, solar gain contributed to uncomfortable internal temperatures; during colder periods, weaker thermal performance increased heat loss. Reflective films added over time created a patchy external appearance without resolving failing units or winter performance.
For Munroe K, the project presented an opportunity to improve the occupier experience and refresh the building’s market-facing appearance while avoiding unnecessary wholesale curtain-wall replacement.
Improved aesthetics
A consistent glazed finish replaces damaged units and years of mismatched applied films.
Better working environment
Reduced glare, lower solar gain and clearer internal views support occupier comfort.
Reduced energy demand
A lower U-value and g-value reduce pressure on heating and air-conditioning systems.
Designed around the constraints of the existing MAG Presslock façade.
The curtain wall incorporated a hard-rubber retaining facecap and a glazing cavity restricted to 12mm. Any replacement unit therefore had to achieve the required performance while remaining compatible with the original system.
Dortech developed the reglazing detail and arranged specially extruded replacement facecaps so the existing framework could remain in service.
Guardian SunGuard Silver 35/26 within the retained curtain wall.
The new insulated glass units were selected to improve solar control, winter insulation and visual consistency. This gave the property owner a practical route to modernise the façade’s performance without removing the complete external envelope.
The result depends as much on compatibility, tolerances and retention detailing as it does on the glass itself.
Lower heat loss and 58% less solar energy transmission through the glass.
A cleaner outlook and a more balanced internal environment.
The new glass replaces aged units and inconsistent films with a coherent specification. Lower solar transmission helps reduce summer overheating, while the improved U-value limits heat loss during colder periods.
For current and prospective occupiers, these changes contribute to comfort, presentation and the perceived quality of the workplace—factors that sit alongside the measurable energy improvements.
Façade performance that can be seen as well as measured.
The improvement is evident both externally, through a more consistent façade, and internally, through cleaner views and reduced glare.
“Literally night and day.”Simon Smithson | Think Architecture
More than an energy project.
For a commercial property owner, façade investment can influence first impressions, occupier satisfaction and the building’s appeal within the leasing market. Reglazing offers a visible transformation while also addressing comfort and energy demand—without the programme and disruption associated with a full curtain-wall replacement.
The project demonstrates how targeted façade investment can support the ongoing repositioning and usability of existing building stock.
Approximately £6,046 to £10,768 in modelled annual savings.
The project assessment indicated approximately £3,269 per year of heating-side savings and £2,777 to £7,499 per year of cooling-side savings based on the glazing replaced to date and the stated assumptions.
Indicative only. Actual savings depend on orientation, occupancy, HVAC controls, internal gains, weather, shading, maintenance, operation and energy prices. No EPC outcome or financial return is guaranteed.
Specialist reglazing turns system constraints into a deliverable project.
White Rose Park shows why large-scale glazing replacement requires more than a glass schedule. Dortech Architectural Systems combines system investigation, glass specification, bespoke interface development, access planning, phased logistics and installation control—allowing clients to improve existing façades that might otherwise appear difficult or uneconomic to upgrade.
See the glazing upgrade in context.



Talk to Dortech Architectural Systems about large-scale specialist reglazing.
We help clients understand whether an existing façade can be retained, how its glass performance can be improved and what is required to deliver the replacement safely at scale.